Cambodia Approves Two 500 kV Transmission Line Projects

The Government of Cambodia’s Council of Ministers approved two 500 kilovolt (kV) transmission line investment projects in (i) Phnom Penh to the Cambodia-Lao PDR border, and (ii) Battambang to the Cambodia-Thailand border, to prepare to import electricity from its neighbors. The Government of Cambodia is working on increasing the country’s electricity capacity to improve production and competitiveness.


The Nam Theun 2 is a 1070 MW hydropower plant on Nam Theun river in Lao PDR. 95% of the power produced by the plant is exported to Thailand and the rest are consumed locally. Revenues from the power plant are used by the government of Lao PDR to help reduce poverty in the country. Photo: ADB

Lao PDR Highlights Dam Safety as Electricity Export Grows

As the Lao People’s Democratic Republic (PDR) increases its electricity exports, the country is prioritizing safety improvement of its dams. A committee comprising local and foreign experts will conduct dam safety inspections, according to news by the Laotian Times. The Government is also implementing new safety measures and standards.


Don Sahong Dam was built by Malaysia’s Mega First Corporation Berhad and EDL-Generation Public Company on the Mekong River in southern Champasak province in Lao PDR. Photo from Khmer Times.

Lao PDR Connects 195 MW Electricity to Cambodia’s National Grid

Tests have been completed on four electricity generators that will link 195 megawatts (MW) of electricity from Don Sahong Dam in Lao People’s Democratic Republic (PDR) to Cambodia’s national grid.